"\

It’s hard to believe that it hasn’t even been a year since Wisteria at Warner Center officially broke ground, especially considering the significant progress we’ve seen on the construction site.

Since our last update, the team has finished grading the residential building, installed primary plumbing and electric conduit, and placed large cisterns for water storage and collection. The photos below illustrate all the hard work they’ve put in.

Now that we’ve finished all the grading and underground work, we’re approved to start pouring the foundation, a monumental next step in our journey to bring The Valley’s newest Life Plan Community to life. Stay tuned for future updates on our progress.

To learn more, give us a call at 1-818-722-6440 to schedule an appointment with a Residency Counselor. We’ll tell you all about how Wisteria will lay the foundation for a wonderful retirement lifestyle with beautiful homes, resort-like amenities, convenient services and so much more.

Concrete forms construction at Wisteria

In the southwest corner of the community, the formwork shapes the edge of the foundation slab.

Electrical construction at Wisteria

The crew runs conduit, which feeds into the electrical rooms.

buried conduit and grading construction at Wisteria

All underground utilities are now in place.